Feni Industry - Kavadarci, R. Macedonia

Project:

Reconstruction of the chain system for transport of raw mine material


Realization of the project:

2011 year


Brief discription:

Reconstruction of the chain system for transport of raw mine material


Realized activities:

  • Dismantling of chain from Lepol Grid (POLYSIUS) with width 4m, length 90 m with a total weight of 120 tons.;
  • Dismantling of supporting and return shafts(Total number- 75 );
  • Dismantling of driving shaft with bearings;
  • Dismantling of return shaft with bearings.

Installation of new equipment:

  • Mounting the complete driving shaft , with sprockets, housings and bearings
  • Installation of complete return shaft
  • Installation of supporting and return shafts with housings and bearings
  • Installation of new chain width 4 m, length 90 m.
  • Installation and rehabilitation of other supporting elements.
  • Alignment and Levelling
  • Putting into operation
  • Total weight of the dismantled and installed new equipment is cca 180 tons.