Ferro Nickel - Kosovo
Project:
Design, Manufacturing, Installation and launching into operation of the reconstructed system for lifting and transporting dust with increased capacity of 40%.
Brief description:
Design, Manufacturing, Installation and launching into operation of the reconstructed system for lifting and transporting dust with increased capacity of 40%, by:
- Increasing the capacity of the elevators on the line 1 and line 2;
- Lead dust from the elevators.
Realized activities:
- Complete replacement of drive unit;
- Complete replacement of take up unit;
- Manufacturing and replacement of buckets for elevators with increased volume;
- Replacement of chains for elevators;
- Reconstruction of unloading of dust;
- Design and manufacture of dust transporters for increased capacity, with a central transport chain;
- Assembly of the overall equipment.
Please contact us for more details!