Project:
Production, supervision during installation and startup of 39 pump aggregates for transport of pit clean and slightly polluted water for the Company Elektroprivreda-Bosnia and Herzegovina.
Brief description:
The pump aggregates are intended for transport of pit clean and slightly polluted water for the Company Elektroprivreda-Bosnia and Herzegovina.
Realized activities:
- Design and production of 4 types of centrifugal pump units for the purpose of Thermal-power plant Kakanj with Capacity up to: Q=3600-4600l/m, H=170m for transport of pit clean and slightly water.
- Design and production of 2 pump units Q=4000m3/h, H=10m, Pm=160kW, n=500 rpm, U=400V;
- Tuzla with Capacity up to: Q=7666l/m, H=190m for transport of pit aggressive wastewater;
- Design and production of centrifugal pump units for the purpose of Black Coal Mine Breza with Capacity up to: Q=4980l/m, H=350m for transport of pit wastewater;
- Design and production of 1 type of multistage centrifugal pump unit for the propose of Black Coal Mine Dzurdzevik with Capacity up to: Q=40-80l/s, H=220m for transport of slightly polluted water;
- Design and production of 1 type of multistage centrifugal pump unit for the purpose of Black Coal Mine Abid Lolic Bila-Travnik with Capacity up to: Q=800-1450l/m, H=252m for transport of slightly polluted water;
- Design and production of 9 types of centrifugal pump unit for the purpose of Black Coal Mine Zenica with Capacity up to: Q=3000l/m, H=170m for transport of pit wastewater;
- Supervision during installation and commissioning.